How to Copy the Working EAC Version to the Approved EAC Version

Goal

After completing this how-to you will have learnt how to copy a working EAC version to an approved EAC version. 

Note that it is only possible to perform this action if the status of all control accounts in the working version are set to approved by the project manager.

First Step

Begin by accessing the Cost Forecasting Dashboard then;

  1. choosing the project in the assigned projects dropdown, 
  2. click the tile labeled "Copy Working to Approved version" in the as shown below;

Second Step

The Plan copy application will be opened and the appropriate EAC versions will be predefined, then simply;

  1. Click Go!

The results of the copy will be displayed.

What's Next

Snapshot the EAC, see the next How-To guide...