How to Update the Forecast for a Project

Goal

After completing this how-to you will have learnt how to update the forecast (also called Estimate to Complete or ETC) for a Project.

First Step

Begin by accessing the Cost Forecasting Dashboard.

  1. Click on the tile labeled "Update ETC with Latest Forecast"

Second Step

Clicking on the tile labeled "Update ETC with Latest Forecast" will launch the EAC Workbench in a new window. This application will be used to manage all the resources necessary for the Work Packages within the Control Accounts which the user is responsible for.

Note that it is also possible to Launch the EAC Workbench by clicking the tile labeled "EAC Workbench".

For a detailed guide about how to use the EAC Workbench to manage resources and submit them for approval, see the following guide;

EAC Workbench

What's Next

Inform the applicable Project Manager that the Forecast is ready for approval.