Goal

After completing this how-to you will have an understanding of the process used to manage the forecast for a project.

First Step

Begin by accessing the Cost Forecasting Dashboard.

Essentially this dashboard outlines the forecasting process (also called Estimate at Completion) for a project. The steps of the process are shown below;

Note that step 1 of the process is performed outside of the Dassian Simple Projects user interface, i.e. the project scheduling tool (Microsoft Project or Oracle Primavera)

What's Next

After the project schedule has been synced with Dassian Simple Projects, continue the process in the Cost Forecasting Dashboard.